South Furious-30 (SF30) Water Flood Phase 2 Project

Award Date : 30 December 2022

Completion Date : 28 May 2024

SEA Hibiscus Sdn. Bhd., an indirect wholly-owned subsidiary of Hibiscus Petroleum Berhad, awarded a contract to Brooke Holding Sdn Bhd, formerly known as Brooke Dockyard and Engineering Works Corporation on December 30, 2022, with commencement on January 16, 2023. The contract encompassed Engineering, Procurement, Construction, Onshore pre-commissioning & commissioning, and Offshore Transportation and Installation for the South Furious-30 (SF30) Water Flood Phase 2 Project.

Adjacent to the SFJT-C platform is the SFJT-D Platform. Situated 205 km northeast of Labuan Island in the waters of Northwest Sabah, placed at a water depth of 18.8 meters, SFJT-D platform is a Not Normally Manned Wellhead Platform (WHP) engineered to manage increased production and transport to the SFP-A processing platform afterwards via the SFJT-C export header and subsea pipelines.

The SFJT-D platform features a template-type 4-legged jacket substructure with piles driven inside or through its legs, weighing a total of 412 metric tons.

The topside of the platform includes a Wellhead Module, refurbished from the decommissioned Tanjong Baram platform topside, and fitted with a new drilling deck extension and weighs 259 MT

The Module Support Frame consist of four level decks: – Cellar Deck, Main Deck, Mezzanine Deck and Upper Deck, weighing a total of 888 MT.
The Wellhead Module was integrated onshore using a heavy lift crane to set down onto the Module Support Frame (MSF), forming the Integrated Topside with a total weight of 1,147 metric tons.