FABRICATION OF WP-IA TOPSIDES

Client : Murphy Sarawak Oil Co LtdAward Date : 11th March 2003Completed Date : 15th August 2003Tonnage : 650MT Another Fast Track Project, Water Injection

JINTAN (JNDRA) TOPSIDES

Award Date : 7th September 2001Completed Date : 26th September 2002Tonnage : 1500MT Another Offshore Drilling Platform Completed by Brooke Dockyard. The Jintan (JNDR-A) Topsides

SFJT-C TOPSIDES

SMART Well Platform built for a Fast track Marginal Field Project Completed in 4 months Client : Sabah Shell Petroleum Co.(SSPC)Award Date : 14h February